Western Corridor 100-Ton Mine Haulage Road & Reinforced Box Culvert Package

Engineering and construction of 9.2 km of heavy-duty industrial mine connector road, 6 multi-cell reinforced concrete box culverts across perennial streams, and gabion slope protection structures.

CLIENT: Birimian Resources Infrastructure Joint Venture
LOCATION: Bogoso–Prestea Corridor, Western Region, Ghana
CONTRACT MODEL: Fixed-Price Civil Works Contract
PROGRAMME DURATION: 10 Months (2024)
HSE RECORD: 215,000 Man-Hours (Zero LTI)
Corridor Length 9.2 km Dual-Lane
Design Axle Load 100-Ton GVW
Box Culverts 6 Multi-Cell Structures
Compaction Spec 98% Mod. AASHTO
Western Corridor 100-Ton Mine Haulage Road & Reinforced Box Culvert Package
SITE PHOTOGRAPH // PRJ-CIV-2408 Bogoso–Prestea Corridor, Western Region, Ghana

Engineering Challenge

Heavy low-bed transport trailers and 45-ton dump trucks operating between active mining pits and regional processing facilities faced severe bottlenecks along a 9.2 km valley corridor prone to seasonal flash flooding and subgrade shear failure. Global World Mining and Construction Limited was contracted to reconstruct the corridor to heavy industrial highway standards without halting ongoing mine logistics.

Technical Execution

1. Subgrade Replacement & Geotextile Separation

Where insitu marshy clays exhibited California Bearing Ratio (CBR) values below 4%, our earthworks fleet excavated up to 1.4 meters depth, installed high-tensile non-woven geotextile separation membranes, and backfilled with graded quarry rock fill compacted via 16-ton vibratory rollers.

2. Multi-Cell Reinforced Concrete Box Culverts

At six perennial river and stream crossings, GWMC constructed twin- and triple-cell 3.0m x 2.5m reinforced concrete box culverts using C35 sulfate-resistant concrete:

  • Temporary cofferdams and dewatering pumps maintained dry foundation excavations while preserving downstream aquatic flow.
  • Flared wingwalls, concrete aprons, and heavy wire-mesh gabion mattresses were installed upstream and downstream to prevent hydraulic scour during 1-in-50-year storm events.

3. Traffic Management & Zero-Disruption Delivery

By executing work in 1.5 km half-width stages with radio-controlled traffic marshals and solar-lit night delineation, mine haulage continued throughout the 10-month programme with zero haulage shutdowns.

Additional Field Documentation